Surplus power for AI training? Why the math doesn't work for GPUs

A new study from MIT and Georgia Tech shows that a grid running on lots of wind and solar regularly ends up with power to spare, and it suggests AI training could soak it up. We ran the numbers the study skips. A data center that only computes during surpluses loses several times more to depreciation than it saves on power. Flexibility can still pay off, just for a different reason.

Analysis Nov 29, 2026 10 min read Original analysis by our editors
Illustrative image, AI-generated

What this is about

On November 24, the journal Joule published a study by Micah Ziegler (now at Georgia Tech), Aliza Khurram, Shannon Hwang and Jessika Trancik (MIT). Their argument: if you build a grid at the lowest possible cost with lots of wind and solar, it will regularly produce more power than anyone can use or store. As buyers for that surplus, the authors name electric arc furnaces for steel, grinding mills, fertilizer and cement production, and they explicitly include AI model training.

The study doesn't answer the obvious question, though: does it pay to run expensive graphics processors (GPUs) only when there's power to spare? We ran those numbers ourselves. The short version: for AI training, the math doesn't work. Data centers can still run flexibly, and that can pay off, but cheap power isn't the reason.

What the Joule study shows and what it leaves out

The researchers simulated an energy system of wind, solar and storage hour by hour over decades. They used 40 years of US weather data including extreme events, regional demand profiles and a range of technology cost assumptions. According to MIT News, in scenarios with 80% renewables, wind and solar can "generate up to 10% more energy than the grid can immediately use or store." At peak times, the surplus output often reaches twice the demand at that moment. The two figures appear to measure different things: one is energy over a full year, the other is power at a given moment.

For planning, what matters is the timing. Surpluses show up mainly in spring and, to a lesser degree, in mid-to-late fall. They usually last 7 to 12 hours at a stretch, from midday into the afternoon, and sometimes for several days. They stay large even if battery storage became ten times cheaper than it is today. Ziegler says:

"There's a huge amount of renewable energy that could be wasted in these cost-optimal systems."

The study doesn't model the costs on the consumer side. According to Scientific Frontline, the authors admit that running expensive computing equipment part-time involves "trade-offs in capital utilization." They suggest less capital-intensive machines and shared facilities. A cost analysis is planned for a follow-up paper.

Our math: what an H100 hour really costs

For our calculation, we assume an Nvidia H100 in a data center you own. According to Morph, an eight-GPU HGX system typically costs around $285,000, or just over $35,000 per GPU. Our other assumptions:

  • Depreciation (the purchase price spread over the years of use), five years: $7,000 per year
  • Cost of capital at 9% on the average capital tied up: about $1,600 per year
  • Space and infrastructure at about $80 per kW per month (method from an analysis of Meta's cluster): about $1,300 per year
  • Power draw: about 1.4 kW per GPU including server and networking (1.37 to 1.39 kW according to SemiAnalysis), times a PUE of 1.25 (PUE measures how much extra power goes to cooling and the building). That comes to about 1.75 kW.
  • Power price: the 2025 US industrial average was 8.62 cents per kWh, according to the EIA. For Germany, the BDEW has so far reported 17.2 euro cents per kWh for small and mid-sized industrial businesses in 2026.

That adds up to fixed costs of about $9,900 per GPU per year, whether the GPU is working or not. Power costs about $0.15 per operating hour in the US and about €0.30 in Germany. At 8,000 compute hours a year, power accounts for about 11% of costs in the US and just under 20% in Germany (to keep it simple, we treated euros and dollars as equal). The Meta analysis lands at a similar 9%. At current rental prices of $3 to $4 per H100 hour (Ornn index: $3.07, Morph median: $4.00), power's share drops to just 4 to 5%. Georgia Tech researchers reach a similar conclusion, according to EPICenter: a GPU rented out at $2 an hour uses only about 4 cents of electricity.

Here's how several operating modes compare. In the best case, the cluster gets free power during surplus windows:

Operating mode (H100, US) Compute hours/year Fixed cost per compute hour Power per hour Cost per compute hour
Around the clock, normal power price 8,000 $1.24 $0.15 $1.39
Surplus windows only, free power 4,000 $2.48 $0 $2.48
Surplus windows only, free power 2,000 $4.96 $0 $4.96
Surplus windows only, free power 1,000 $9.92 $0 $9.92

Our own calculation, assumptions above. The study's public summaries don't say how many surplus hours occur per year, so the hour figures are scenarios.

Running only on surplus power costs the same as running around the clock only at about 7,100 compute hours a year. That means the cluster would have to run in more than 80% of all hours of the year. In Germany, where power costs more, the break-even point is about 6,400 hours. Surplus windows of 7 to 12 hours a day, mostly in spring, come nowhere close. A cluster running only 2,000 hours would also need four times as many GPUs to deliver the same compute. The B200 is no better: according to Morph, it costs $30,000 to $50,000 per GPU and draws 1,000 watts, so capital weighs even more.

Our take: fully depreciated hardware doesn't change much either. According to Morph, H100 rental prices rose 17% in 90 days. Every hour a GPU sits idle is rental income you lose.

What can be shifted technically

You can pause a training run. Checkpoints, which are progress snapshots saved at regular intervals, let you pick up right where you left off. But pausing isn't cheap. For models with 70 billion parameters or more, saving a checkpoint takes 5 to 15 minutes while the GPUs sit waiting, according to the GoCkpt paper. Just setting up communication between 2,048 GPUs takes about 1,000 seconds, according to the FFTrainer paper. And interruptions happen all the time: training Llama 3 on 16,384 H100s saw 419 unplanned interruptions in 54 days.

For the grid, sudden load swings are the bigger problem. In its Llama 3 report, Meta described simultaneous power swings of tens of megawatts. According to EE Power, US grid regulator NERC issued its highest-level alert in May 2026 after more than 1,000 MW of compute load dropped off the grid within seconds in one incident. A data center that ramps up every day when the sun is highest and back down in the evening has to make those ramps smooth.

Besides training, batch inference (requests that are collected and processed later) and data preparation count as shiftable. Real-time chat doesn't. An analysis by Meiyi Li using operating data from 155,410 GPUs shows how small that shiftable share is: on average, only 12.1% of the compute load could be throttled right away. That's 6.35% of the facility's total load. According to the paper, the fixed flexibility percentages used in grid studies overstate the actual relief by 17 to 47%.

What the pilot projects measure

Project What was measured
Emerald AI, Oracle, Nvidia, SRP in Phoenix (256 GPUs) 25% less power for 3 hours, ramped down over 15 minutes, 24 hours' notice
Emerald AI, Nebius, National Grid near London (96 Blackwell Ultra GPUs) up to 40% less within one minute, according to heise, around 200 simulated grid events
Google 1 GW of demand response in contracts with I&M, TVA and other utilities, according to the Google blog

All three projects are demand response: the grid operator can ask for the load to be cut for a few hours on short notice. That's far from operating around the weather. According to Latitude Media, the Phoenix test covered only the compute loads, not cooling or backup power. Nvidia is both a partner in and an investor in Emerald AI. Google itself writes that its flexibility is limited and available only at certain sites.

The 2025 Duke study shows how much even a little flexibility would help the grid. If large consumers cut their load in an average of 0.25% of hours, about 22 hours a year, the US could absorb 76 GW of additional load. At 1% (about 88 hours), it would be 126 GW. That's where the economic payoff is: if you're willing to cut back occasionally, you get connected to the grid faster. According to heise, National Grid hopes to cut wait times from about ten years to two. An MIT study in iScience adds a caveat: flexible data centers lower system costs by 2 to 5%, but in the Mid-Atlantic grid they could keep coal plants running longer and raise emissions by 3%.

What this means for Germany

In 2025, Germany curtailed around 9.4 TWh of renewable power, meaning it wasn't generated because the grid couldn't carry it. That's 3.5% of renewable generation. According to ZfK, compensation for it came to €433 million, and congestion management cost about €3.1 billion in total. There were also 573 hours of negative wholesale prices, 234 of them in spring. Our math shows how little that does for a data center: even with free power in all 573 hours, an H100 saves about €170 a year. Its fixed costs are nearly 10,000.

According to ladefreun.de, the "Use instead of curtail" program ("Nutzen statt Abregeln") under §13k EnWG, in trial since October 2024, is designed for three groups: replacing fossil heat, storage, and electrolyzers plus large heat pumps. Data centers aren't a separate group. Results so far are thin: according to Enertrag, the 45 MW power-to-heat plant "Karoline" in Hamburg took part for about 150 hours in 2025, and the verdict was "pretty sobering." In the consultation on Germany's data center strategy, the provider Loadwise calls for variable grid fees and flexible connection agreements, among other things. Meanwhile, the first projects are getting started on the coast. According to Datacenter-Insider, a 150 to 300 MW campus is planned in Langenhorn, pitched on the back of surplus wind power. In Handewitt, an AI data center with battery storage and up to 200 MVA of connection capacity is planned.

The bottom line

The Joule study gives a useful forecast of when power will be left over. But its idea of AI training as a buyer for that power doesn't hold up. For GPUs, capital is the biggest cost and power is a minor one. In our math, a cluster that runs only when the weather allows costs three to seven times as much per compute hour as one running around the clock. If you want to use surplus power, you need equipment that's cheap to buy, like electrolyzers, heat pumps or immersion heaters. That's essentially what the authors say too.

Our take: what pays off for data centers is something else. They can offer a small amount of reliable flexibility, a few dozen hours a year, in exchange for a faster grid connection. A data center on the North Sea does have advantages: green power is easier to get there, the grid connection may come sooner, and the air for cooling is cooler. It will still run its GPUs around the clock. Two questions remain open: how many surplus hours the Joule model actually produces, and how the math changes if GPU prices ever drop sharply. Our figures are an example calculation based on publicly available values, not a real operator's numbers.

Sources

#data centers#energy#gpu costs#power grid#renewables

Ask the AI assistant

Questions about this article, installation or background? Our assistant knows this page and runs on our own machine, not in someone else's cloud.

Connecting …

The Assistant is an AI (Gemma 4) and can make mistakes – please check important details against the source. Questions are used only to generate an answer and are deleted after one hour. Please don't enter any personal data.